{"success":true,"data":{"pressRelease":{"id":"148290","rtpr_id":"nNFC6HlvHK-20260921","ticker":"AMX","exchange":"","all_tickers":["AMX"],"title":"Amex Gold Mining Provides Update on Development Activities at the Perron Project - More than 75 m of Underground Decline Development Completed","author":"Newsfile Corp","published_at":"2026-09-21T11:00:22.738Z","article_body":"Montreal, Quebec--(Newsfile Corp. - September 21, 2026) - Amex Gold Mining\nInc. (TSXV: AMX) (FSE: MX00) (OTCQX: AMXEF) (\"Amex\" or the \"Company\") is\npleased to provide an update on development activities at its 100%-owned\nPerron Gold Project, located near Normétal, Quebec. Please view video here:\nhttps://youtu.be/rMp5CVNU53Q\n\nCannot view this video? Visit:\nhttps://www.youtube.com/watch?v=rMp5CVNU53Q\n\nFollowing the successful completion of portal construction and the\ncommencement of underground development, the decline has now advanced more\nthan 75 metres underground as part of Amex's permitted 40,000-tonne bulk\nsample program.\n\nIn parallel, Amex continues to advance key surface infrastructure at Perron.\nConstruction of the mechanical shop has commenced, while clearing of the\nright-of-way for the 25 kV power line has been completed. Installation of the\npower line poles is expected to begin in the coming weeks.\n\nRecent and ongoing activities at Perron include:\n* More than 75 metres of underground decline development completed,\nrepresenting another important milestone in the advancement of the bulk sample\nprogram;\n* Construction of the mechanical shop has commenced, providing permanent\ninfrastructure to support underground equipment and site activities;\n* Clearing of the right-of-way for the 25 kV power line has been completed,\nwith pole installation scheduled to begin in the coming weeks;\n* Continued underground development toward the high-grade Champagne Zone;\n* Continued operation and optimization of the site's water treatment\ninfrastructure;\n* Ongoing development of surface infrastructure, laydown areas and services\nrequired to support underground activities; and\n* Continued planning and engineering for additional infrastructure required at\nPerron.\nThe ongoing work is being completed as part of a broader effort to\nprogressively establish the infrastructure required at Perron while advancing\nthe 40,000-tonne bulk sample program. The program is designed to provide\nimportant technical information on underground mining conditions, grade\ncontinuity, dilution, mining recovery, and metallurgical performance of the\nhigh-grade Champagne Zone.\n\nVictor Cantore, President and CEO of Amex Gold Mining, commented:\n\"Reaching the first 75 metres of underground development is another important\nmilestone for Perron. Since commencing underground development, we have\ncontinued to make steady progress below surface while simultaneously advancing\nseveral important infrastructure projects at site.\"\n\n\"With construction of the mechanical shop underway, the power line\nright-of-way cleared, and pole installation expected to begin shortly, the\nPerron site continues to evolve rapidly. We remain focused on safely and\nefficiently executing the bulk sample program while progressively putting in\nplace the infrastructure required to support the project's continued\ndevelopment.\"\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_002full.jpg)\n\nUnderground Portal\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_002full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_003full.jpg)\n\nOverall site layout\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_003full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_004full.jpg)\n\nWater treatment plant\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_004full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_005full.jpg)\n\nPad for maintenance shop and dome\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_005full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_006full.jpg)\n\nUnderground ramp\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_006full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_007full.jpg)\n\nTree line cut for future 25 kV power line\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_007full.jpg\n\nAbout Amex\nAmex Gold Mining Inc. has made significant high-grade gold discoveries, along\nwith copper-rich volcanogenic massive sulphide (VMS) zones, at its 100%-owned\nPerron Gold Project. It is located in the territory of Valcanton in northern\nQuebec, approximately 110 kilometres north of Rouyn-Noranda.\n\nThe Perron Project in Quebec consists of 183 contiguous claims for a surface\narea of 65.72 km². The project hosts several zones of high-grade gold\nmineralization, VMS mineralization and 'hybrid' gold-rich VMS mineralization.\n\nWhen combined with the adjacent and contiguous Perron West Project and\nAbbotsford and Hepburn Projects (including additional claims acquired through\nstaking) in Ontario, the consolidated land package spans a district-scale\n570.94 km². This extensive property lies within highly prospective geology\nfavourable for both high-grade gold and VMS mineralization.\n\nThe Project benefits from excellent infrastructure: it is accessible by a\nyear-round road, located just 30 minutes from an airport, and approximately\n6.5 km from the Town of Normétal. Being in close proximity to several\nprocessing plants owned by major gold producers also constitutes a strategic\nadvantage.\n\nQualified Person\n\nThe technical information in this news release has been reviewed and approved\nby Aaron Stone, P.Geo (OGQ - 2170, PGO - 3708), Vice President Exploration of\nthe Company, acting as a Qualified Person within the meaning of National\nInstrument 43-101.\n\nFor further information please contact:\nVictor Cantore\nPresident and Chief Executive Officer\nAmex Gold Mining Inc.: +1-514-866-8209\nNeither the TSX Venture Exchange nor its Regulation Services Provider (as that\nterm is defined in the policies of the TSX Venture Exchange) accepts\nresponsibility for the adequacy or accuracy of this release.\n\nForward-looking statements\n\nThis News Release contains forward-looking statements. All statements, other\nthan statements of historical fact, contained in this News Release including,\nbut not limited to those describing the impact of the foregoing on the Perron\nGold Project economics, results of the feasibility study for the Phase 1\ndevelopment of the Perron Gold Project announced by Amex Gold Mining Inc.\n(\"Amex\" or the \"Company\") on April 13, 2026 (the \"Feasibility Study\" or \"FS\")\n(as such results are commented in the text of this News Release), including\nCAPEX, OPEX, NPV and IRR, the estimated value of the Perron Gold Project,\noperations development scenarios for the Perron Gold Project, commercial and\ntechnical parameters, the attractive economics for the Perron Gold Project,\nLOM plans, the Company's intended marketing strategy, market trends, future\ngold prices, the impact of the Perron Gold Project on the local communities,\nincluding job creation, the projected annual production of the Company's\noperations, the timelines and costs related to the various initiatives,\ndeliverables and milestones described in this News Release and their expected\nresults, the Company's expected financial and operational performance, the\nnature of relationships with stakeholders such as the local community\nincluding the Abitibiwinni First Nation, Mineral Resource estimates (including\nassumptions and estimates used in preparing the Mineral Resource estimates),\nthe general business and operational outlook of the Company, the Company's\nfuture growth and business prospects, and those statements which are discussed\nelsewhere in the News Release which essentially describe the Company's outlook\nand objectives, constitute \"forward-looking information\" or \"forward-looking\nstatements\" (collectively, \"forward-looking statements\") within the meaning of\napplicable Canadian securities laws, and are based on expectations, estimates\nand projections as of the time of this News Release. Forward-looking\nstatements are necessarily based upon a number of estimates and assumptions\nthat, while considered reasonable by the Company as of the time of such\nstatements, are inherently subject to significant business, economic and\ncompetitive uncertainties and contingencies. These estimates and assumptions\nmay prove to be incorrect. Moreover, these forward-looking statements were\nbased upon various underlying factors and assumptions, including the business\nrelationship between the Company and its stakeholders, the ability to operate\nin a safe and effective manner, the timely delivery and installation at\nestimated prices of the equipment supporting the production, assumed sale\nprices for gold, the accuracy of any Mineral Resource estimates, future\ncurrency exchange rates and interest rates, political and regulatory\nstability, prices of commodity and production costs, the receipt of\ngovernmental, regulatory and third party approvals, licenses and permits on\nfavourable terms, sustained labour stability, stability in financial and\ncapital markets, availability of equipment and critical supplies, spare parts\nand consumables, various tax assumptions, CAPEX and OPEX estimates, the Perron\nGold Project permits' status, all economic and operational projections\nrelating to the project, local infrastructures, the Company's business\nprospects and opportunities and estimates of the operational performance of\nthe equipment, and are not guarantees of future performance. Forward-looking\nstatements are subject to known or unknown risks and uncertainties that may\ncause actual results to differ materially from those anticipated or implied in\nthe forward-looking statements. Risk factors that could cause actual results\nor events to differ materially from current expectations include, among\nothers, delays in the scheduled delivery times of equipment, the ability of\nthe Company to successfully implement its strategic initiatives and whether\nsuch strategic initiatives will yield the expected benefits, the availability\nof financing or financing on favorable terms for the Company, the dependence\non commodity prices, the impact of inflation on costs, the risks of obtaining\nthe necessary permits, the operating performance of the Company's assets and\nbusinesses, competitive factors in the gold mining and production industry,\nchanges in laws and regulations affecting the Company's businesses, political\nand social acceptability risk, environmental regulation risk, currency and\nexchange rate risk, technological developments, and general economic\nconditions, as well as earnings, capital expenditure, cash flow and capital\nstructure risks and general business risks. A further description of risks\nand uncertainties can be found in the Company's annual Management's Discussion\nand Analysis, including in the section thereof captioned \"Risk Factors\", which\nis available on sedarplus.ca\n(https://api.newsfilecorp.com/redirect/XENayUWg50). Unpredictable or unknown\nfactors not discussed in this Cautionary Note could also have material adverse\neffects on forward-looking statements. Many of these uncertainties and\ncontingencies can directly or indirectly affect, and could cause, actual\nresults to differ materially from those expressed or implied in any\nforward-looking statements. There can be no assurance that forward-looking\nstatements will prove to be accurate, as actual results and future events\ncould differ materially from those anticipated in such statements.\nForward-looking statements are provided for the purpose of providing\ninformation about management's expectations and plans relating to the future.\nThe Company disclaims any intention or obligation to update or revise any\nforward-looking statements or to explain any material difference between\nsubsequent actual events and such forward-looking statements, except to the\nextent required by applicable law.\n\n\nTo view the source version of this press release, please visit\nhttps://www.newsfilecorp.com/release/315157","article_body_html":"","raw_payload":{"data":{"id":"nNFC6HlvHK-20260921","title":"Amex Gold Mining Provides Update on Development Activities at the Perron Project - More than 75 m of Underground Decline Development Completed","author":"Newsfile Corp","ticker":"AMX","created":"2026-09-21T11:00:22.738Z","tickers":["AMX"],"exchange":"","article_body":"Montreal, Quebec--(Newsfile Corp. - September 21, 2026) - Amex Gold Mining\nInc. (TSXV: AMX) (FSE: MX00) (OTCQX: AMXEF) (\"Amex\" or the \"Company\") is\npleased to provide an update on development activities at its 100%-owned\nPerron Gold Project, located near Normétal, Quebec. Please view video here:\nhttps://youtu.be/rMp5CVNU53Q\n\nCannot view this video? Visit:\nhttps://www.youtube.com/watch?v=rMp5CVNU53Q\n\nFollowing the successful completion of portal construction and the\ncommencement of underground development, the decline has now advanced more\nthan 75 metres underground as part of Amex's permitted 40,000-tonne bulk\nsample program.\n\nIn parallel, Amex continues to advance key surface infrastructure at Perron.\nConstruction of the mechanical shop has commenced, while clearing of the\nright-of-way for the 25 kV power line has been completed. Installation of the\npower line poles is expected to begin in the coming weeks.\n\nRecent and ongoing activities at Perron include:\n* More than 75 metres of underground decline development completed,\nrepresenting another important milestone in the advancement of the bulk sample\nprogram;\n* Construction of the mechanical shop has commenced, providing permanent\ninfrastructure to support underground equipment and site activities;\n* Clearing of the right-of-way for the 25 kV power line has been completed,\nwith pole installation scheduled to begin in the coming weeks;\n* Continued underground development toward the high-grade Champagne Zone;\n* Continued operation and optimization of the site's water treatment\ninfrastructure;\n* Ongoing development of surface infrastructure, laydown areas and services\nrequired to support underground activities; and\n* Continued planning and engineering for additional infrastructure required at\nPerron.\nThe ongoing work is being completed as part of a broader effort to\nprogressively establish the infrastructure required at Perron while advancing\nthe 40,000-tonne bulk sample program. The program is designed to provide\nimportant technical information on underground mining conditions, grade\ncontinuity, dilution, mining recovery, and metallurgical performance of the\nhigh-grade Champagne Zone.\n\nVictor Cantore, President and CEO of Amex Gold Mining, commented:\n\"Reaching the first 75 metres of underground development is another important\nmilestone for Perron. Since commencing underground development, we have\ncontinued to make steady progress below surface while simultaneously advancing\nseveral important infrastructure projects at site.\"\n\n\"With construction of the mechanical shop underway, the power line\nright-of-way cleared, and pole installation expected to begin shortly, the\nPerron site continues to evolve rapidly. We remain focused on safely and\nefficiently executing the bulk sample program while progressively putting in\nplace the infrastructure required to support the project's continued\ndevelopment.\"\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_002full.jpg)\n\nUnderground Portal\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_002full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_003full.jpg)\n\nOverall site layout\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_003full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_004full.jpg)\n\nWater treatment plant\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_004full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_005full.jpg)\n\nPad for maintenance shop and dome\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_005full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_006full.jpg)\n\nUnderground ramp\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_006full.jpg\n\n(https://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_007full.jpg)\n\nTree line cut for future 25 kV power line\n\nTo view an enhanced version of this graphic, please visit:\nhttps://images.newsfilecorp.com/files/2667/315157_151b7b1b34a6b981_007full.jpg\n\nAbout Amex\nAmex Gold Mining Inc. has made significant high-grade gold discoveries, along\nwith copper-rich volcanogenic massive sulphide (VMS) zones, at its 100%-owned\nPerron Gold Project. It is located in the territory of Valcanton in northern\nQuebec, approximately 110 kilometres north of Rouyn-Noranda.\n\nThe Perron Project in Quebec consists of 183 contiguous claims for a surface\narea of 65.72 km². The project hosts several zones of high-grade gold\nmineralization, VMS mineralization and 'hybrid' gold-rich VMS mineralization.\n\nWhen combined with the adjacent and contiguous Perron West Project and\nAbbotsford and Hepburn Projects (including additional claims acquired through\nstaking) in Ontario, the consolidated land package spans a district-scale\n570.94 km². This extensive property lies within highly prospective geology\nfavourable for both high-grade gold and VMS mineralization.\n\nThe Project benefits from excellent infrastructure: it is accessible by a\nyear-round road, located just 30 minutes from an airport, and approximately\n6.5 km from the Town of Normétal. Being in close proximity to several\nprocessing plants owned by major gold producers also constitutes a strategic\nadvantage.\n\nQualified Person\n\nThe technical information in this news release has been reviewed and approved\nby Aaron Stone, P.Geo (OGQ - 2170, PGO - 3708), Vice President Exploration of\nthe Company, acting as a Qualified Person within the meaning of National\nInstrument 43-101.\n\nFor further information please contact:\nVictor Cantore\nPresident and Chief Executive Officer\nAmex Gold Mining Inc.: +1-514-866-8209\nNeither the TSX Venture Exchange nor its Regulation Services Provider (as that\nterm is defined in the policies of the TSX Venture Exchange) accepts\nresponsibility for the adequacy or accuracy of this release.\n\nForward-looking statements\n\nThis News Release contains forward-looking statements. All statements, other\nthan statements of historical fact, contained in this News Release including,\nbut not limited to those describing the impact of the foregoing on the Perron\nGold Project economics, results of the feasibility study for the Phase 1\ndevelopment of the Perron Gold Project announced by Amex Gold Mining Inc.\n(\"Amex\" or the \"Company\") on April 13, 2026 (the \"Feasibility Study\" or \"FS\")\n(as such results are commented in the text of this News Release), including\nCAPEX, OPEX, NPV and IRR, the estimated value of the Perron Gold Project,\noperations development scenarios for the Perron Gold Project, commercial and\ntechnical parameters, the attractive economics for the Perron Gold Project,\nLOM plans, the Company's intended marketing strategy, market trends, future\ngold prices, the impact of the Perron Gold Project on the local communities,\nincluding job creation, the projected annual production of the Company's\noperations, the timelines and costs related to the various initiatives,\ndeliverables and milestones described in this News Release and their expected\nresults, the Company's expected financial and operational performance, the\nnature of relationships with stakeholders such as the local community\nincluding the Abitibiwinni First Nation, Mineral Resource estimates (including\nassumptions and estimates used in preparing the Mineral Resource estimates),\nthe general business and operational outlook of the Company, the Company's\nfuture growth and business prospects, and those statements which are discussed\nelsewhere in the News Release which essentially describe the Company's outlook\nand objectives, constitute \"forward-looking information\" or \"forward-looking\nstatements\" (collectively, \"forward-looking statements\") within the meaning of\napplicable Canadian securities laws, and are based on expectations, estimates\nand projections as of the time of this News Release. Forward-looking\nstatements are necessarily based upon a number of estimates and assumptions\nthat, while considered reasonable by the Company as of the time of such\nstatements, are inherently subject to significant business, economic and\ncompetitive uncertainties and contingencies. These estimates and assumptions\nmay prove to be incorrect. Moreover, these forward-looking statements were\nbased upon various underlying factors and assumptions, including the business\nrelationship between the Company and its stakeholders, the ability to operate\nin a safe and effective manner, the timely delivery and installation at\nestimated prices of the equipment supporting the production, assumed sale\nprices for gold, the accuracy of any Mineral Resource estimates, future\ncurrency exchange rates and interest rates, political and regulatory\nstability, prices of commodity and production costs, the receipt of\ngovernmental, regulatory and third party approvals, licenses and permits on\nfavourable terms, sustained labour stability, stability in financial and\ncapital markets, availability of equipment and critical supplies, spare parts\nand consumables, various tax assumptions, CAPEX and OPEX estimates, the Perron\nGold Project permits' status, all economic and operational projections\nrelating to the project, local infrastructures, the Company's business\nprospects and opportunities and estimates of the operational performance of\nthe equipment, and are not guarantees of future performance. Forward-looking\nstatements are subject to known or unknown risks and uncertainties that may\ncause actual results to differ materially from those anticipated or implied in\nthe forward-looking statements. Risk factors that could cause actual results\nor events to differ materially from current expectations include, among\nothers, delays in the scheduled delivery times of equipment, the ability of\nthe Company to successfully implement its strategic initiatives and whether\nsuch strategic initiatives will yield the expected benefits, the availability\nof financing or financing on favorable terms for the Company, the dependence\non commodity prices, the impact of inflation on costs, the risks of obtaining\nthe necessary permits, the operating performance of the Company's assets and\nbusinesses, competitive factors in the gold mining and production industry,\nchanges in laws and regulations affecting the Company's businesses, political\nand social acceptability risk, environmental regulation risk, currency and\nexchange rate risk, technological developments, and general economic\nconditions, as well as earnings, capital expenditure, cash flow and capital\nstructure risks and general business risks. A further description of risks\nand uncertainties can be found in the Company's annual Management's Discussion\nand Analysis, including in the section thereof captioned \"Risk Factors\", which\nis available on sedarplus.ca\n(https://api.newsfilecorp.com/redirect/XENayUWg50). Unpredictable or unknown\nfactors not discussed in this Cautionary Note could also have material adverse\neffects on forward-looking statements. Many of these uncertainties and\ncontingencies can directly or indirectly affect, and could cause, actual\nresults to differ materially from those expressed or implied in any\nforward-looking statements. There can be no assurance that forward-looking\nstatements will prove to be accurate, as actual results and future events\ncould differ materially from those anticipated in such statements.\nForward-looking statements are provided for the purpose of providing\ninformation about management's expectations and plans relating to the future.\nThe Company disclaims any intention or obligation to update or revise any\nforward-looking statements or to explain any material difference between\nsubsequent actual events and such forward-looking statements, except to the\nextent required by applicable law.\n\n\nTo view the source version of this press release, please visit\nhttps://www.newsfilecorp.com/release/315157"},"type":"article","timestamp":"2026-09-21T11:00:22.790552457Z","server_sent_at_ms":1789988422790},"received_at":"2026-09-21T11:00:22.846Z","source_url":"https://www.newsfilecorp.com/release/315157"},"analysis":{"id":"137785","press_release_id":"148290","analysis_json":{"industry":{"label":"Gold","sector":"Materials"},"redFlags":[],"eventType":"operations_update","narrative":"Amex Gold Mining has advanced more than 75 metres of underground decline development at its 100%-owned Perron Gold Project in Quebec, a milestone within its permitted 40,000-tonne bulk sample program.\n\nSurface infrastructure is progressing in parallel: construction of the mechanical shop has commenced, the right-of-way for the 25 kV power line is fully cleared, and pole installation is expected to begin in the coming weeks.\n\nUnderground development continues toward the high-grade Champagne Zone, and the bulk sample is designed to deliver technical data on mining conditions, grade continuity, dilution, mining recovery, and metallurgical performance.","sentiment":"bullish","agentHooks":{"shouldPost":false,"suggestedAngle":"Decline development past 75 m keeps Amex on schedule toward its 40,000-tonne bulk sample — first bulk sample grades are the next real catalyst."},"keyFigures":{"customDimensions":{"contiguous_claims":183,"powerline_voltage_kv":25,"perron_property_area_km2":65.72,"bulk_sample_program_tonnage":40000,"consolidated_land_package_km2":570.94,"distance_from_normetal_town_km":6.5,"decline_development_completed_m":75,"distance_north_of_rouyn_noranda_km":110}},"quotedText":"Reaching the first 75 metres of underground development is another important milestone for Perron.","namedEntities":{"people":[{"name":"Victor Cantore","role":"President and CEO"},{"name":"Aaron Stone","role":"Vice President Exploration / Qualified Person (P.Geo)"}],"products":["Perron Gold Project","Champagne Zone","Perron West Project","Abbotsford and Hepburn Projects"],"companies":[{"name":"Amex Gold Mining Inc.","ticker":"AMX","relationship":"filer"}],"dollarAmounts":[]},"materialImpact":{"score":2,"reasoning":"Routine execution milestones at the Perron Gold Project (75+ m of decline development, mechanical shop start, power-line right-of-way cleared) with no new financials, resource estimates, or timeline changes. Positive de-risking signal for the bulk sample program, but limited market-moving content."},"tickerRelevance":{"others":[{"ticker":"AMXEF","relevance":"OTCQX alternate listing of the filer"},{"ticker":"MX00","relevance":"Frankfurt (FSE) alternate listing of the filer"}],"primary":"AMX"},"globalImportance":16,"audienceRelevance":14,"eventTypeSecondary":[],"importanceComponents":{"tickerTier":"micro-cap junior gold miner (TSXV)","eventGravity":"routine_operational_milestone","sectorWeight":"materials_gold","issuerAuthored":true,"marketCapAdjustment":"no dollar figures or resource updates disclosed","retailFavoriteBoost":"minor - junior explorer with niche retail following"}},"event_type":"operations_update","event_type_secondary":null,"sentiment":"bullish","material_impact_score":2,"narrative":"Amex Gold Mining has advanced more than 75 metres of underground decline development at its 100%-owned Perron Gold Project in Quebec, a milestone within its permitted 40,000-tonne bulk sample program.\n\nSurface infrastructure is progressing in parallel: construction of the mechanical shop has commenced, the right-of-way for the 25 kV power line is fully cleared, and pole installation is expected to begin in the coming weeks.\n\nUnderground development continues toward the high-grade Champagne Zone, and the bulk sample is designed to deliver technical data on mining conditions, grade continuity, dilution, mining recovery, and metallurgical performance.","key_figures":{"customDimensions":{"contiguous_claims":183,"powerline_voltage_kv":25,"perron_property_area_km2":65.72,"bulk_sample_program_tonnage":40000,"consolidated_land_package_km2":570.94,"distance_from_normetal_town_km":6.5,"decline_development_completed_m":75,"distance_north_of_rouyn_noranda_km":110}},"named_entities":{"people":[{"name":"Victor Cantore","role":"President and CEO"},{"name":"Aaron Stone","role":"Vice President Exploration / Qualified Person (P.Geo)"}],"products":["Perron Gold Project","Champagne Zone","Perron West Project","Abbotsford and Hepburn Projects"],"companies":[{"name":"Amex Gold Mining Inc.","ticker":"AMX","relationship":"filer"}],"dollarAmounts":[]},"model_name":"glm-5.3-flash","prompt_hash":"sha256:727b4b9429a443af","schema_hash":"sha256:05005c02d9cffac9","created_at":"2026-09-22T08:55:56.376Z","global_importance":16,"audience_relevance":14,"importance_components":{"tickerTier":"micro-cap junior gold miner (TSXV)","eventGravity":"routine_operational_milestone","sectorWeight":"materials_gold","issuerAuthored":true,"marketCapAdjustment":"no dollar figures or resource updates disclosed","retailFavoriteBoost":"minor - junior explorer with niche retail following"}},"durationMs":113495,"modelName":"glm-5.3-flash"}}